Case Study: Double Mezzanine & Fit Out, Gloucester

Turnkey Mezzanine & Fit Out Project, Gloucester

Complete design and build of a double fire rated mezzanine floor in Gloucester designed for storage and offices.

• Mezzanine floors were 76m2 and 36m2.
• Full CAD/CAM design with structural calculations.
• Before installation began, we sealed the floor and laid an epoxy floor coating.
• Upon design sign off, manufacturing was quickly undertaken and steelwork erected over several days.
• Once the structure was built, it was ’fire rated’ and suspended ceiling installed to comply with Building Control Regulations.
• We then knocked through the wall between buildings and created a new fire exit joining the two mezzanines.
• Open plan offices were built using stud and plasterboard in a tape joint and emulsion finish and carpets laid.
• A glass feature wall was installed on the mezzanine edge providing a panoramic view of the factory.
• Building control approval was undertaken by Advantage making the end to end process extremely straight forward for the customer.
• All our mezzanines are provided with CE mark certification and full loading and structural calculations.

CALL NOW for more information: 01905 622830 or Email: sales@advantage-uk.com

About Advantage Mezzanines

Advantage has specialised in the design and installation of mezzanine floors and their associated services for more than 25 years, providing our services to hundreds of clients nationwide. Read more

How can we help?

Get in touch with our sales team who will be happy to discuss your needs and provide you with a no-obligation quote.