Storage Mezzanine Case Studies: |
|
Furniture Retailer Worcestershire |
|
On-Line Warehouse Facility Nottingham |
|
Printing Manufacturer, Worcestershire, Working Out
of Hours |
|
UK Distribution Centre, Gloucestershire, Storage
Space Doubled |
|
National Distribution Warehouse, Tewksbury |
|
On Line Distribution Warehouse, Worcestershire,
Built in 2 days |
|
Hydraulic Filtration Equipment Manufacturer,
Cotswolds |
|
Facilities Management Central Stores, Malvern,
Completed one weekend |
|
Furniture Manufacturer, West Midlands |
|
Automotive Distributor, Worcestershire, Before
and After Photographs |
|
Plastic Mouldings Manufacturer, Worcestershire,
Built in one weekend |
|
National Distribution Warehouse, Gloucester |
 |
|
| |
|
|
|
|
|
FREE no-obligation
consultation, advice
and quotation:
Call 01905 622 830 |
|
Printing Manufacturer,
Worcestershire, Working Out of Hours
When a local printers went digital, it became apparent that the unit into
which they had moved in 2003 could not accommodate both the new CDI platesetter,
6 colour label printer machine and the opportunity for business expansion that
the new technology would bring.
A move was rejected since this would result in delays in production which
would affect their service to key clients.
Advantage installed a fire rated mezzanine, increasing the capacity of the
existing factory premises by 50%. This made space available on the ground floor
for the installation of new machinery to enable our client to meet the challenge
of the business expansion predicted in the years to come.
To minimise disruption, it was essential that contamination of the clean
printing environment demanded by the food industry was kept to a minimum. It was
also a requirement of the project that there was no disruption to production
during construction. This necessitated carrying out the mezzanine build between
5.00pm and 1.00am.
|
Click in image(s) for larger versions: |
| |
|
|
 |
|
|
| |
|
|
|